Please be advised that our Customer Service offices will be closed for the festive period from 12pm on Tuesday, December 24 reopening again as usual on Thursday, January 2 from 8.30am. If you need urgent assistance during this time, please call (03) 5358 8700. For more information on other service closures and contact information, please visit the below web page.
View Holiday Closure Information
This council led project will map flooding throughout the St Arnaud township to inform design and infrastructure needs to manage water flows into the future.
As a part of the St Arnaud Flood Study, Watertech has put together various flood maps modelling the significant rain event in November 2018. Data used includes photos from council and community members, impact data and local water system assessments.
January 2020 - March 2020
The draft flood maps were tested with the St Arnaud community to determine accuracy and provide additional input prior to presenting these to the broader community.
March 2020
Finalisation of flood maps, reflective of community input. Reports will include mitigation options, property impact and future planning overlays.
October 2020 - October 2022
Presentation of final study. Once finalised, the study will be incorporated into emergency management, planning reforms and infrastructure improvements so flood events can be better managed and controlled when they do occur.
March 2023
Infrastructure Team
Nic Murphy
ngshire@ngshire.vic.gov.au
03 5358 8700
St-Arnaud-Flood-Study-Final-Summary-Report(PDF, 9MB)