Our building and planning teams have implemented a new and simple permit application process called Greenlight. The Greenlight Online Permit Manager will allow you to submit and pay for your applications online, receive correspondence by email and monitor the status of your applications from start to finish. To access, please visit our planning or building permit pages or click on the link:
Northern Grampians Shire Greenlight Planning and Building Permits
This council led project will map flooding throughout the St Arnaud township to inform design and infrastructure needs to manage water flows into the future.
As a part of the St Arnaud Flood Study, Watertech has put together various flood maps modelling the significant rain event in November 2018. Data used includes photos from council and community members, impact data and local water system assessments.
January 2020 - March 2020
The draft flood maps were tested with the St Arnaud community to determine accuracy and provide additional input prior to presenting these to the broader community.
March 2020
Finalisation of flood maps, reflective of community input. Reports will include mitigation options, property impact and future planning overlays.
October 2020 - October 2022
Presentation of final study. Once finalised, the study will be incorporated into emergency management, planning reforms and infrastructure improvements so flood events can be better managed and controlled when they do occur.
March 2023
Infrastructure Team
Nic Murphy
ngshire@ngshire.vic.gov.au
03 5358 8700
St-Arnaud-Flood-Study-Final-Summary-Report(PDF, 9MB)